The proposed Puketoi Wind Farm is on the Puketoi Range approximately 50 kilometres south-east of Palmerston North. Work is under way to progress this consented site to a shovel-ready project including baseline ecological surveys, transport route analysis, further site investigations and development of design.
Project status: Consented with Tararua District Council, Palmerston North City Council and Horizons Regional Council, with a resource consent extension to 2031 to start construction. Location: The wind farm site (and almost all of the transmission line) is in Tararua District, 40km south of Dannevirke and 39km east of the Turitea Wind Farm. Maximum capacity: of around 228MW, generating approximately 1,040GWh per year Turbines: 53 turbines Blade tip height: 160m Transmission connection: The Turitea transmission line was designed with spare capacity to connect Puketoi.